Bassetlaw: housing land supply and delivery
Bassetlaw delivered 357% of the homes it needed in the three years to 31 March 2025. That passes the test and carries no consequence, so whether the unmet-need route opens turns on the five-year supply.
357%
Housing Delivery Test 2025
2,899 homes delivered against 812 required, 2022-23 to 2024-25
95% or more: no consequenceHousing Delivery Test 2025
Homes needed and homes built
| Year | Homes required | Homes built |
|---|---|---|
| 2022-23 | 279 | 1,046 |
| 2023-24 | 273 | 981 |
| 2024-25 | 260 | 872 |
| Three years | 812 | 2,899 |
Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.
At planning committee
Committee approval rate
Committee approval rate
85.9%
Of 71 decisions taken at Bassetlaw’s planning committee in Searchland’s data, 85.9% were approved.
Source: Searchland, Committee Explorer, authority export, read 27 October 2026.
The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.
From the council’s own documents
Supply, plan and levy
Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.
Five-year housing land supply
5.31 years
At 1 April 2025, five years or more on the council’s own figure. The figure is measured against the adopted Local Plan requirement of 540 homes a year plus a 5% buffer. The council says a 2026-2031 position statement will be published later in 2026.
Source: Bassetlaw District Council Five Year Housing Supply Position Statement, 1 April 2025 – 31 March 2030, published March 2026.
Local plan
Bassetlaw Local Plan 2020-2038
Adopted 29 May 2024. Made neighbourhood plans and the Nottinghamshire Minerals and Waste Local Plans also form part of the development plan.
The council is preparing a new Bassetlaw Local Plan under the new plan-making system. It published its notice of intention on 11 June 2026 and held a scoping consultation from 3 September to 15 October 2026. Its timetable has the formal 30-month process starting on 30 October 2026, submission for examination in March 2028 and a decision on adoption in April 2029.
Sources: the adopted plan; Bassetlaw Local Plan timetable, September 2026. Status checked 24 October 2026.
Community Infrastructure Levy, 2026
Residential, per m²
| Homes (C3), whole district | £21.00 |
| Local Plan housing allocations of 50 or more homes | £0 (nil) |
These rates apply to permissions granted on or after 1 June 2024. Older permissions granted from 1 September 2013 to 31 May 2024 pay the zoned 2013 schedule rates (2026 indexed: £98.21, £35.71 and £8.93 per m2 for homes).
Source: How much will my CIL charge be? (Annual Rate Summary 2026, Charging Schedule 2024).
Under the NPPF
What the result means for a site
The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.
A result of 95% or more carries none of the Framework's consequences. The test on its own does not deem an unmet need for housing to exist.
On the council’s own figure of 5.31 years (below) the council can demonstrate a five-year supply, so the unmet-need route in policy S5(1)(j) is not open on supply either. Supply figures are often contested at appeal, and a later finding can differ.
The Bassetlaw Local Plan 2020-2038 was adopted on 29 May 2024. Until 29 May 2029, a local housing need figure above the plan's requirement is not, by itself, evidence of unmet need.
“Where a local planning authority can demonstrate a five year supply of deliverable housing sites (with the appropriate buffer) and where the Housing Delivery Test indicates that the delivery of housing is more than 75% of the housing requirement over the previous three years, for the purposes of policy S5(1)(j), if the most up-to-date local housing need figure (calculated using the standard method set out in Annex D) is greater than the housing requirement set out in adopted development plan policies, this should not be considered as evidence of unmet need, for a period of five years from the date of the plan's adoption.”
NPPF, Annex A, paragraph 3, page 99
In the Green Belt
Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.
“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”
NPPF, Footnote 41, page 63
What it does not do
None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.
“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”
NPPF, Policy S5(2), page 26
Across the boundary
Councils next to Bassetlaw
A site near the edge of Bassetlaw may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.
| Council | HDT 2025 | Five-year supply | Committee approval rate |
|---|---|---|---|
| Bolsover | 205% 95% or more: no consequence | 4.82 years at 1 April 2026 | Not available |
| Doncaster | 213% 95% or more: no consequence | 6.35 years at 1 April 2025 | 82.9% of 35 |
| Mansfield | 134% 95% or more: no consequence | 5.53 years at 1 April 2026 | 88.9% of 117 |
| Newark and Sherwood | 139% 95% or more: no consequence | 4.02 years at 1 April 2026 | 72% of 567 |
| North Lincolnshire | 137% 95% or more: no consequence | Not yet checked | 81.1% of 228 |
| Rotherham | 139% 95% or more: no consequence | 4.41 years at 1 April 2025 | 79.3% of 256 |
| West Lindsey | 141% 95% or more: no consequence | 7.8 years at 1 April 2024 (out of date) | Not available |
Councils that share a boundary with Bassetlaw on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.
Check a site in Bassetlaw
Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.
Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.