Bracknell Forest delivered 104% of the homes it needed in the three years to 31 March 2025. That passes the test and carries no consequence, so whether the unmet-need route opens turns on the five-year supply.

104%

Housing Delivery Test 2025

1,778 homes delivered against 1,715 required, 2022-23 to 2024-25

95% or more: no consequence

Housing Delivery Test 2025

Homes needed and homes built

YearHomes requiredHomes built
2022-23586438
2023-24566924
2024-25563416
Three years1,7151,778

Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.

At planning committee

Committee approval rate

Committee approval rate

78.7%

Of 950 decisions taken at Bracknell Forest’s planning committee in Searchland’s data, 78.7% were approved.

Source: Searchland, Committee Explorer, authority export, read 27 October 2026.

The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.

From the council’s own documents

Supply, plan and levy

Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.

Five-year housing land supply

3.53 years

At 1 April 2026, under five years on the council’s own figure. The figure uses the Local Plan requirement of 614 homes a year with a 20% buffer, because that requirement is 78% of the standard method figure of 787. The note was revised in August 2026 for the new NPPF.

Source: BFC HLS calculation at 1 April 2026 (Revised August 2026), published August 2026.

Local plan

Bracknell Forest Local Plan to 2037

Adopted 19 March 2024. Some policies of the Site Allocations Local Plan (July 2013), five made neighbourhood plans and the Joint Minerals and Waste Plan (2023) are also part of the development plan.

The council's Local Development Scheme of March 2025 plans an update of the Local Plan under the new plan-making system, with scoping and a call for sites in 2026/2027. It puts submission to the Secretary of State in autumn 2029.

Sources: the adopted plan; Local Development Scheme 2025 to 2028, March 2025. Status checked 25 October 2026.

Community Infrastructure Levy, 2026

Residential, per m²

Homes, Northern Parishes, 1 to 14 homes£540.54
Homes, Northern Parishes, 15 or more homes£339.77
Homes, Crowthorne and Sandhurst, 1 to 14 homes£463.32
Homes, Crowthorne and Sandhurst, 15 or more homes£231.66
Homes, Outer Bracknell, 1 to 14 homes£115.83
Homes, Outer Bracknell, 15 or more homes£38.61

These are the 2026 rates for homes (use class C3), indexed from the 2015 charging schedule. Named strategic sites have their own rates, and the zones are mapped in the charging schedule.

Source: CIL rates page (2026 rates with RICS BCIS CIL Index increase).

Under the NPPF

What the result means for a site

The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.

A result of 95% or more carries none of the Framework's consequences. The test on its own does not deem an unmet need for housing to exist.

The unmet-need route in policy S5(1)(j) is still open in Bracknell Forest, because the council’s own figure is under five years of supply (below). Policy S5(1)(j) applies where the council “cannot demonstrate a five year supply of deliverable housing sites or scores below 75% in the most recent Housing Delivery Test”.

In the Green Belt

Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.

“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”

NPPF, Footnote 41, page 63

What it does not do

None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.

“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”

NPPF, Policy S5(2), page 26

Across the boundary

Councils next to Bracknell Forest

A site near the edge of Bracknell Forest may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.

CouncilHDT 2025Five-year supplyCommittee approval rate
Hart137% 95% or more: no consequence2.07 years at 1 April 202585.1% of 121
Surrey Heath98% 95% or more: no consequence3.12 years at 1 April 202575.2% of 444
Windsor and Maidenhead74% Under 75%: unmet need deemed4.04 years at 1 April 2024 (out of date)66.9% of 375
Wokingham100% 95% or more: no consequence2.5 years at 31 March 202591.5% of 340

Councils that share a boundary with Bracknell Forest on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.

Check a site in Bracknell Forest

Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.

Check a site in Bracknell Forest

Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.