Canterbury delivered 79% of the homes it needed in the three years to 31 March 2025. That puts a 20% buffer on its five-year supply and requires an action plan. On its own it does not open the unmet-need route for sites outside settlements.

79%

Housing Delivery Test 2025

2,645 homes delivered against 3,345 required, 2022-23 to 2024-25

Under 85%: 20% buffer and action plan

Housing Delivery Test 2025

Homes needed and homes built

YearHomes requiredHomes built
2022-231,058690
2023-241,146723
2024-251,1411,232
Three years3,3452,645

Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.

At planning committee

Committee approval rate

Committee approval rate

82.9%

Of 643 decisions taken at Canterbury’s planning committee in Searchland’s data, 82.9% were approved.

Source: Searchland, Committee Explorer, authority export, read 27 October 2026.

The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.

From the council’s own documents

Supply, plan and levy

Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.

Five-year housing land supply

3.62 years

At 1 April 2025, under five years on the council’s own figure. The five-year period runs from 1 April 2025 to 31 March 2030, measured against local housing need because the 2017 plan is more than five years old.

Source: Authority Monitoring Report April 2024 to March 2025 (Housing Land Supply Statement appendix), published December 2025.

Local plan

Canterbury District Local Plan 2011-2031

Adopted 13 July 2017. In Herne Bay it is read with the Herne Bay Area Action Plan 2010.

The Draft Canterbury District Local Plan was consulted on under Regulation 19 from 23 March to 18 May 2026. The council's consultation page gives the next step as "Draft Local Plan Submission (September to December 2026)". No submission date or Inspector had been published by 22 October 2026.

Sources: the adopted plan; Regulation 19 consultation page, checked 22 October 2026. Status checked 22 October 2026.

Community Infrastructure Levy

Not yet checked

Whether Canterbury charges CIL, and at what rate this year, has not yet been checked for this page.

Under the NPPF

What the result means for a site

The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.

The result is below 85%, so from 18 August 2026 the council must prepare an action plan and add a 20% buffer to its five-year supply. The published result is not below 75%, so the test does not on its own deem an unmet need for housing to exist.

“Where delivery falls below 85% of the requirement over the previous three years, a buffer of 20% should be added to the identified supply of specific deliverable sites. This is in addition to the requirement for an action plan;”

NPPF, Annex D, paragraph 12(b), page 119

The unmet-need route in policy S5(1)(j) is still open in Canterbury, because the council’s own figure is under five years of supply (below). Policy S5(1)(j) applies where the council “cannot demonstrate a five year supply of deliverable housing sites or scores below 75% in the most recent Housing Delivery Test”.

In the Green Belt

Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.

“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”

NPPF, Footnote 41, page 63

What it does not do

None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.

“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”

NPPF, Policy S5(2), page 26

Across the boundary

Councils next to Canterbury

A site near the edge of Canterbury may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.

CouncilHDT 2025Five-year supplyCommittee approval rate
Ashford75% Under 85%: 20% buffer and action plan3.62 years at 1 April 202677.5% of 307
Dover108% 95% or more: no consequence4.8 years at 1 April 202676% of 592
Folkestone and Hythe57% Under 75%: unmet need deemed3.1 years at 1 April 2024 (out of date)83% of 348
Swale70% Under 75%: unmet need deemed3.48 years at 1 April 202578.2% of 156
Thanet70% Under 75%: unmet need deemed3.7 years at 31 March 202586.7% of 833

Councils that share a boundary with Canterbury on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.

Check a site in Canterbury

Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.

Check a site in Canterbury

Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.