East Hertfordshire: housing land supply and delivery

East Hertfordshire delivered 102% of the homes it needed in the three years to 31 March 2025. That passes the test and carries no consequence, so whether the unmet-need route opens turns on the five-year supply.

102%

Housing Delivery Test 2025

2,909 homes delivered against 2,840 required, 2022-23 to 2024-25

95% or more: no consequence

Housing Delivery Test 2025

Homes needed and homes built

YearHomes requiredHomes built
2022-23840889
2023-249601,265
2024-251,041755
Three years2,8402,909

Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.

At planning committee

Committee approval rate

Committee approval rate

80.4%

Of 586 decisions taken at East Hertfordshire’s planning committee in Searchland’s data, 80.4% were approved.

Source: Searchland, Committee Explorer, authority export, read 27 October 2026.

The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.

From the council’s own documents

Supply, plan and levy

Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.

Five-year housing land supply

Not yet checked

The council publishes its own five-year supply statement. Land Pass has not yet checked the current figure for East Hertfordshire.

Local plan

East Herts District Plan 2018

Adopted 23 October 2018. The plan runs from 2011 to 2033.

Work has started on a new Local Plan to 2044 under the new plan-making system. The council's indicative timetable puts the first consultation on the plan's content from 22 February to 5 April 2027, submission on 2 October 2028 and adoption on 2 April 2029. No draft strategy, site list or housing figure had been published by 9 October 2026.

Sources: the adopted plan; Council's local plan timetable page, checked 9 October 2026. Status checked 9 October 2026.

Community Infrastructure Levy, 2026

No CIL in force

East Hertfordshire has no CIL charging schedule in force. Contributions are secured through Section 106 agreements.

Source: Council's Section 106 agreements page.

Under the NPPF

What the result means for a site

The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.

A result of 95% or more carries none of the Framework's consequences. The test on its own does not deem an unmet need for housing to exist.

Whether policy S5(1)(j) opens in East Hertfordshire therefore turns on the five-year supply: it opens if the council cannot demonstrate one. Land Pass has not yet checked the council's current figure for this page.

In the Green Belt

Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.

“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”

NPPF, Footnote 41, page 63

What it does not do

None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.

“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”

NPPF, Policy S5(2), page 26

Across the boundary

Councils next to East Hertfordshire

A site near the edge of East Hertfordshire may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.

CouncilHDT 2025Five-year supplyCommittee approval rate
Broxbourne110% 95% or more: no consequence2.13 years at 1 April 202576% of 125
Epping Forest66% Under 75%: unmet need deemed4.22 years at 1 April 202572% of 765
Harlow91% Under 95%: action plan3.1 years at 31 March 202690.9% of 285
North Hertfordshire75% Under 85%: 20% buffer and action plan2.43 years at 1 April 202683.2% of 382
Stevenage78% Under 85%: 20% buffer and action plan5.59 years at 1 April 2024 (out of date)93.8% of 240
Uttlesford108% 95% or more: no consequenceNo published figure found72.6% of 581
Welwyn Hatfield46% Under 75%: unmet need deemed1.8 years at 1 April 202578.1% of 288

Councils that share a boundary with East Hertfordshire on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.

Check a site in East Hertfordshire

Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.

Check a site in East Hertfordshire

Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.