Enfield: housing land supply and delivery
Enfield delivered 77% of the homes it needed in the three years to 31 March 2025. That puts a 20% buffer on its five-year supply and requires an action plan. On its own it does not open the unmet-need route for sites outside settlements.
77%
Housing Delivery Test 2025
2,862 homes delivered against 3,738 required, 2022-23 to 2024-25
Under 85%: 20% buffer and action planHousing Delivery Test 2025
Homes needed and homes built
| Year | Homes required | Homes built |
|---|---|---|
| 2022-23 | 1,246 | 892 |
| 2023-24 | 1,246 | 872 |
| 2024-25 | 1,246 | 1,097 |
| Three years | 3,738 | 2,862 |
Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.
At planning committee
Committee approval rate
Committee approval rate
88.1%
Of 177 decisions taken at Enfield’s planning committee in Searchland’s data, 88.1% were approved.
Source: Searchland, Committee Explorer, authority export, read 27 October 2026.
The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.
From the council’s own documents
Supply, plan and levy
Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.
Five-year housing land supply
3.1 years
At 1 April 2024, the latest figure the council has published. It is more than a year old, so this page does not rely on it. Checked 25 October 2026. The figure is measured against the London Plan 2021 target of 1,246 homes a year with a 20% buffer, giving 4,641 deliverable homes for 2024 to 2029.
Source: Authority Monitoring Report 2023/24 including Five Year Housing Land Supply, published Not dated in the document; the supply position it reports was published on 1 November 2024.
Local plan
The Enfield Plan: Core Strategy 2010-2025
Adopted 10 November 2010. The Development Management Document (adopted November 2014), three area action plans, the North London Waste Plan 2022, the Hadley Wood Neighbourhood Plan and the London Plan are also part of the development plan.
The new Enfield Local Plan 2019-2041 is at examination. The hearings closed on 19 March 2026 and the Inspector sent his post-hearing advice on 15 June 2026. On 29 June 2026 the council said it was preparing main modifications, with consultation expected later in 2026.
Sources: the adopted plan; Initial Council Response to Inspector's Post Hearing advice (IN14), 29 June 2026. Status checked 25 October 2026.
Community Infrastructure Levy, 2026
Residential, per m²
| Homes, Meridian Water Masterplan area (RR1) | £0 (nil) |
| Homes, lower rate zone, eastern corridor (RR2) | £59.25 |
| Homes, intermediate rate zone (RR3) | £88.88 |
| Homes, higher rate zone, rest of the borough (RR4) | £177.77 |
Rates for permissions granted in 2026; the Mayor of London's CIL (MCIL2, £72.72 per square metre in 2026) is charged on top.
Source: Annual CIL Rate Summary 2026.
Under the NPPF
What the result means for a site
The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.
The result is below 85%, so from 18 August 2026 the council must prepare an action plan and add a 20% buffer to its five-year supply. The published result is not below 75%, so the test does not on its own deem an unmet need for housing to exist.
“Where delivery falls below 85% of the requirement over the previous three years, a buffer of 20% should be added to the identified supply of specific deliverable sites. This is in addition to the requirement for an action plan;”
NPPF, Annex D, paragraph 12(b), page 119
Whether policy S5(1)(j) opens in Enfield therefore turns on the five-year supply: it opens if the council cannot demonstrate one. The council's latest published figure, 3.1 years at 1 April 2024, is more than a year old, so it is not a safe guide to the position now.
In the Green Belt
Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.
“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”
NPPF, Footnote 41, page 63
What it does not do
None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.
“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”
NPPF, Policy S5(2), page 26
Across the boundary
Councils next to Enfield
A site near the edge of Enfield may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.
| Council | HDT 2025 | Five-year supply | Committee approval rate |
|---|---|---|---|
| Barnet | 97% 95% or more: no consequence | Not yet checked | 79.2% of 1,703 |
| Broxbourne | 110% 95% or more: no consequence | 2.13 years at 1 April 2025 | 76% of 125 |
| Epping Forest | 66% Under 75%: unmet need deemed | 4.22 years at 1 April 2025 | 72% of 765 |
| Haringey | 71% Under 75%: unmet need deemed | 5.18 years at 31 March 2024 (out of date) | 86.3% of 320 |
| Hertsmere | 26% Under 75%: unmet need deemed | No published figure found | 79% of 1,023 |
| Waltham Forest | 84% Under 85%: 20% buffer and action plan | 5.21 years at 1 April 2025 | 91.4% of 394 |
| Welwyn Hatfield | 46% Under 75%: unmet need deemed | 1.8 years at 1 April 2025 | 78.1% of 288 |
Councils that share a boundary with Enfield on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.
Check a site in Enfield
Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.
Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.