Horsham: housing land supply and delivery
Horsham delivered 44% of the homes it needed in the three years to 31 March 2025. Under the NPPF in force since 17 August 2026, that means an evidenced unmet need for housing is deemed to exist.
44%
Housing Delivery Test 2025
1,217 homes delivered against 2,776 required, 2022-23 to 2024-25
Under 75%: unmet need deemedHousing Delivery Test 2025
Homes needed and homes built
| Year | Homes required | Homes built |
|---|---|---|
| 2022-23 | 948 | 414 |
| 2023-24 | 911 | 461 |
| 2024-25 | 917 | 342 |
| Three years | 2,776 | 1,217 |
Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published. gov.uk’s table labels this band “Presumption”, the name it had before the August 2026 Framework.
At planning committee
Committee approval rate
Committee approval rate
71.4%
Of 1,257 decisions taken at Horsham’s planning committee in Searchland’s data, 71.4% were approved.
Source: Searchland, Committee Explorer, authority export, read 27 October 2026.
The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.
From the council’s own documents
Supply, plan and levy
Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.
Five-year housing land supply
1.0 years
Agreed at appeal APP/Z3825/W/24/3355546, decided 11 July 2025.
Source: Appeal decision APP/Z3825/W/24/3355546 (Horsham Golf Club, Denne Park), published 11 July 2025.
Local plan
Horsham District Planning Framework (HDPF), 2015
Adopted 27 November 2015. The HDPF covers the district outside the South Downs National Park; made neighbourhood plans and older site allocations documents also form part of the development plan.
The Horsham District Local Plan 2023-2040 was submitted for examination on 26 July 2024. After hearings in December 2024 and April 2026, the council consulted on main modifications from 13 July to 24 August 2026, and further hearing sessions were scheduled from 13 to 23 October 2026. Separately, the council published notice on 25 June 2026 that it is starting a new-system plan, Horsham District 2045, with the formal 30-month preparation expected to begin on 1 November 2026.
Sources: the adopted plan; Latest News from Local Plan Examination, council web page, latest entry 23 October 2026; Horsham District 2045 page with the Notice of Intention to Commence, published 25 June 2026. Status checked 25 October 2026.
Community Infrastructure Levy, 2026
Residential, per m²
| Homes, district wide (Zone 1) | £188.81 |
| Homes, strategic sites (Zone 2) | £0 (nil) |
Rates for permissions granted in 2026; zone maps are in the council's April 2017 CIL Charging Schedule, and the part of the district in the South Downs National Park is charged under the National Park Authority's own schedule.
Under the NPPF
What the result means for a site
The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.
The result is below 75%, so all three of the Framework's consequences apply in Horsham from 18 August 2026, the day after publication. The council must prepare an action plan and add a 20% buffer to its five-year supply, and an evidenced unmet need for housing is deemed to exist.
“Where delivery falls below 75% of the requirement over the previous three years, an evidenced unmet need for housing is deemed to exist for the purpose of applying policy S5(1)(j) in this Framework. This is in addition to the requirements for an action plan and 20% buffer.”
NPPF, Annex D, paragraph 12(c), pages 119 to 120
That unmet need is what policy S5(1)(j) turns on. Outside settlements, housing that is physically well related to an existing settlement, and of a scale the infrastructure can take, is among the forms of development that should be approved unless the benefits are substantially outweighed by the adverse effects.
“Development which would address an evidenced unmet need (including, but not limited to, development proposals involving the provision of housing where the local planning authority cannot demonstrate a five year supply of deliverable housing sites or scores below 75% in the most recent Housing Delivery Test), and where the development would: i. Be physically well-related to an existing settlement (unless the nature of the development would make this inappropriate) and be of a scale which can be accommodated taking into account the existing or proposed availability of infrastructure; or ii. Comprise major development for freight and logistics purposes which accords with policy E3.”
NPPF, Policy S5(1)(j), page 26
In the Green Belt
Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.
“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”
NPPF, Footnote 41, page 63
What it does not do
None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.
“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”
NPPF, Policy S5(2), page 26
Across the boundary
Councils next to Horsham
A site near the edge of Horsham may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.
| Council | HDT 2025 | Five-year supply | Committee approval rate |
|---|---|---|---|
| Adur | 48% Under 75%: unmet need deemed | 3.2 years at 1 April 2025 | 88.5% of 52 |
| Arun | 84% Under 85%: 20% buffer and action plan | 3.23 years at 31 March 2025 | 85.4% of 466 |
| Brighton and Hove | 50% Under 75%: unmet need deemed | 1.5 years at 1 April 2025 | 82.4% of 1,134 |
| Chichester | 124% 95% or more: no consequence | 4.52 years at 1 July 2026 | 84.6% of 467 |
| Crawley | 36% Under 75%: unmet need deemed | 5.4 years at 31 March 2024 (out of date) | 87.4% of 230 |
| Mid Sussex | 104% 95% or more: no consequence | 5.04 years at 1 April 2023 (out of date) | 89.7% of 389 |
| Mole Valley | 72% Under 75%: unmet need deemed | 5.3 years at 31 March 2026 | 88.3% of 77 |
| Waverley | 117% 95% or more: no consequence | 1.28 years at 1 April 2024 (out of date) | 71% of 903 |
Councils that share a boundary with Horsham on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.
Check a site in Horsham
Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.
Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.