Councils · England
Huntingdonshire: housing land supply and delivery
Huntingdonshire delivered 136% of the homes it needed in the three years to 31 March 2025. That passes the test and carries no consequence, so whether the unmet-need route opens turns on the five-year supply.
136%
Housing Delivery Test 2025
3,369 homes delivered against 2,474 required, 2022-23 to 2024-25
95% or more: no consequenceHousing Delivery Test 2025
Homes needed and homes built
| Year | Homes required | Homes built |
|---|---|---|
| 2022-23 | 804 | 1,238 |
| 2023-24 | 804 | 1,264 |
| 2024-25 | 866 | 866 |
| Three years | 2,474 | 3,369 |
Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.
At planning committee
Committee approval rate
Committee approval rate
Not available
Huntingdonshire is not in Searchland’s export.
Source: Searchland, Committee Explorer, authority export, read 27 October 2026.
The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.
From the council’s own documents
Supply, plan and levy
Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.
Five-year housing land supply
3.68 years
At 31 March 2025, under five years on the council’s own figure. This is measured against the standard method figure of 1,232 homes a year, less past oversupply, with a 5% buffer; the report gives the position as at 31 March 2025, and the council's Monitoring page still states 3.68 years as the current position.
Source: Annual Monitoring Report 2025 Part 1 (Housing Supply), published November 2025.
Local plan
Huntingdonshire's Local Plan to 2036
Adopted 15 May 2019. Made neighbourhood plans and the Cambridgeshire and Peterborough Minerals and Waste Local Plan are also part of the development plan.
The council is preparing a Local Plan to 2046. Its Pre-Submission (Regulation 19) consultation runs from 16 September to 28 October 2026. The council intends to submit the plan for examination by the end of December 2026, with hearings expected in 2027.
Sources: the adopted plan; Pre-Submission Local Plan to 2046 (Regulation 19 publication), council web page, read 25 October 2026. Status checked 25 October 2026.
Community Infrastructure Levy, 2026
Residential, per m²
| Homes (standard rate, whole district) | £152.47 |
Homes pay the standard rate for permissions granted in 2026; care homes and other Class C2 uses pay £80.72 per square metre.
Source: Huntingdonshire District Council Community Infrastructure Levy (CIL) Annual Rate Summary 2026.
Under the NPPF
What the result means for a site
The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.
A result of 95% or more carries none of the Framework's consequences. The test on its own does not deem an unmet need for housing to exist.
The unmet-need route in policy S5(1)(j) is still open in Huntingdonshire, because the council’s own figure is under five years of supply (below). Policy S5(1)(j) applies where the council “cannot demonstrate a five year supply of deliverable housing sites or scores below 75% in the most recent Housing Delivery Test”.
In the Green Belt
Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.
“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”
NPPF, Footnote 41, page 63
What it does not do
None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.
“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”
NPPF, Policy S5(2), page 26
Across the boundary
Councils next to Huntingdonshire
A site near the edge of Huntingdonshire may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.
| Council | HDT 2025 | Five-year supply | Committee approval rate |
|---|---|---|---|
| Bedford | 94% Under 95%: action plan | 3.24 years at 1 April 2026 | 69.1% of 191 |
| Central Bedfordshire | 105% 95% or more: no consequence | 3.93 years at 1 April 2026 | 81.8% of 696 |
| East Cambridgeshire | 116% 95% or more: no consequence | 6.17 years at 1 April 2025 | 65.7% of 207 |
| Fenland | 117% 95% or more: no consequence | Not yet checked | 72.1% of 685 |
| North Northamptonshire | 108% 95% or more: no consequence | Not yet checked | 91.3% of 321 |
| Peterborough | 100% 95% or more: no consequence | 4.38 years at 31 March 2025 | 68.1% of 499 |
| South Cambridgeshire | 148% 95% or more: no consequence | 7.83 years at 1 April 2026 | 70.4% of 825 |
Councils that share a boundary with Huntingdonshire on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.
Check a site in Huntingdonshire
Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.
Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.