If we think you should walk away, we will say so. Free first pass, answered in two working days ·  Send a site
Land PassIndependent land checks

Councils · England

Maidstone: housing land supply and delivery

Maidstone delivered 93% of the homes it needed in the three years to 31 March 2025. That requires the council to prepare an action plan. On its own it does not open the unmet-need route for sites outside settlements.

93%

Housing Delivery Test 2025

2,784 homes delivered against 3,000 required, 2022-23 to 2024-25

Under 95%: action plan

Housing Delivery Test 2025

Homes needed and homes built

YearHomes requiredHomes built
2022-231,0001,064
2023-241,0001,066
2024-251,000654
Three years3,0002,784

Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.

At planning committee

Committee approval rate

Committee approval rate

84.6%

Of 1,340 decisions taken at Maidstone’s planning committee in Searchland’s data, 84.6% were approved.

Source: Searchland, Committee Explorer, authority export, read 27 October 2026.

The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.

From the council’s own documents

Supply, plan and levy

Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.

Five-year housing land supply

Not yet checked

The council publishes its own five-year supply statement. Land Pass has not yet checked the current figure for Maidstone.

Local plan

Maidstone Local Plan Review 2021-2038

Adopted 20 March 2024.

Maidstone is preparing a new Local Plan. Its consultation portal invites anyone promoting land to put sites forward for the new plan. The call for sites was set to run first from 15 June 2026 to midnight on 23 August 2026, and the portal still takes submissions, with an estimated end of 31 December 2027.

Sources: the adopted plan; Maidstone Call for Sites 2026, the council's consultation portal, read 25 October 2026. Status checked 25 October 2026.

Community Infrastructure Levy

Not yet checked

Whether Maidstone charges CIL, and at what rate this year, has not yet been checked for this page.

Under the NPPF

What the result means for a site

The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.

The result is below 95%, so from 18 August 2026 the council must prepare an action plan. The published result is not below 75%, so the test does not on its own deem an unmet need for housing to exist.

“Where delivery falls below 95% of the requirement over the previous three years, the authority should prepare an action plan to assess the causes of under-delivery and identify actions to increase delivery in the future;”

NPPF, Annex D, paragraph 12(a), page 119

Whether policy S5(1)(j) opens in Maidstone therefore turns on the five-year supply: it opens if the council cannot demonstrate one. Land Pass has not yet checked the council's current figure for this page.

In the Green Belt

Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.

“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”

NPPF, Footnote 41, page 63

What it does not do

None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.

“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”

NPPF, Policy S5(2), page 26

Across the boundary

Councils next to Maidstone

A site near the edge of Maidstone may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.

CouncilHDT 2025Five-year supplyCommittee approval rate
Ashford75% Under 85%: 20% buffer and action plan3.62 years at 1 April 202677.5% of 307
Medway60% Under 75%: unmet need deemed3.1 years at 1 April 202576.2% of 1,377
Swale70% Under 75%: unmet need deemed3.48 years at 1 April 202578.2% of 156
Tonbridge and Malling63% Under 75%: unmet need deemed2.96 years at 31 March 202666.7% of 306
Tunbridge Wells93% Under 95%: action plan4.7 years at 1 April 202683.8% of 606

Councils that share a boundary with Maidstone on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.

Check a site in Maidstone

Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.

Check a site in Maidstone

Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.