Councils · England
Reigate and Banstead: housing land supply and delivery
Reigate and Banstead delivered 102% of the homes it needed in the three years to 31 March 2025. That passes the test and carries no consequence, so whether the unmet-need route opens turns on the five-year supply.
102%
Housing Delivery Test 2025
1,411 homes delivered against 1,384 required, 2022-23 to 2024-25
95% or more: no consequenceHousing Delivery Test 2025
Homes needed and homes built
| Year | Homes required | Homes built |
|---|---|---|
| 2022-23 | 461 | 686 |
| 2023-24 | 461 | 505 |
| 2024-25 | 461 | 220 |
| Three years | 1,384 | 1,411 |
Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.
At planning committee
Committee approval rate
Committee approval rate
90.9%
Of 11 decisions taken at Reigate and Banstead’s planning committee in Searchland’s data, 90.9% were approved.
Source: Searchland, Committee Explorer, authority export, read 27 October 2026.
The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.
From the council’s own documents
Supply, plan and levy
Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.
Five-year housing land supply
4.08 years
At 31 March 2026, under five years on the council’s own figure. The figure is measured against the Core Strategy requirement of 460 homes a year, which the council reviewed in 2024 and found not to need updating, with a 20% buffer because that requirement is below 80% of the standard method figure.
Source: Housing Delivery Monitor Including 5 Year Housing Land Supply, Position at 31 March 2026 (Housing Monitor 2026), published 2026.
Local plan
Reigate & Banstead Local Plan: Core Strategy
Adopted 3 July 2014. The Development Management Plan (adopted 2019) and the policies map are also part of the local plan; the council reviewed the Core Strategy on 2 July 2019 and 28 March 2024 and found it did not need updating.
Reigate & Banstead is preparing a new Local Plan 2044 under the new plan-making system, and gave its notice to commence on 31 July 2026. A scoping consultation runs from 14 September to 26 October 2026, with Gateway 1 expected in December 2026. The timetable shows submission for examination in December 2028 and adoption in June 2029, and the council becomes part of a new East Surrey unitary authority in April 2027.
Sources: the adopted plan; Local Plan 2044 timetable page, Reigate & Banstead Borough Council, read 24 October 2026. Status checked 24 October 2026.
Community Infrastructure Levy, 2026
Residential, per m²
| Homes (Use Class C3), Charge Zone 1 | £0 (nil) |
| Homes (Use Class C3), Charge Zone 2 | £206.64 |
| Homes (Use Class C3), Charge Zone 3 | £118.08 |
| Homes (Use Class C3), Charge Zone 4 | £265.68 |
| Homes (Use Class C3), Charge Zone 5 | £295.20 |
These are the 2016 charging schedule's rates indexed for 2026.
Source: Annual CIL rate Summary 2026.
Under the NPPF
What the result means for a site
The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.
A result of 95% or more carries none of the Framework's consequences. The test on its own does not deem an unmet need for housing to exist.
The unmet-need route in policy S5(1)(j) is still open in Reigate and Banstead, because the council’s own figure is under five years of supply (below). Policy S5(1)(j) applies where the council “cannot demonstrate a five year supply of deliverable housing sites or scores below 75% in the most recent Housing Delivery Test”.
In the Green Belt
Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.
“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”
NPPF, Footnote 41, page 63
What it does not do
None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.
“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”
NPPF, Policy S5(2), page 26
Across the boundary
Councils next to Reigate and Banstead
A site near the edge of Reigate and Banstead may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.
| Council | HDT 2025 | Five-year supply | Committee approval rate |
|---|---|---|---|
| Crawley | 36% Under 75%: unmet need deemed | 5.4 years at 31 March 2024 (out of date) | 87.4% of 230 |
| Croydon | 105% 95% or more: no consequence | 5.1 years at 31 March 2024 (out of date) | 83% of 653 |
| Epsom and Ewell | 33% Under 75%: unmet need deemed | Not yet checked | 79.6% of 230 |
| Mole Valley | 72% Under 75%: unmet need deemed | 5.3 years at 31 March 2026 | 88.3% of 77 |
| Sutton | 81% Under 85%: 20% buffer and action plan | 8.8 years at 1 April 2026 | 89.3% of 1,079 |
| Tandridge | 38% Under 75%: unmet need deemed | 2.17 years at 1 October 2025 | 67.7% of 164 |
Councils that share a boundary with Reigate and Banstead on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.
Check a site in Reigate and Banstead
Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.
Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.