Councils · England

West Suffolk: housing land supply and delivery

West Suffolk delivered 89% of the homes it needed in the three years to 31 March 2025. That requires the council to prepare an action plan. On its own it does not open the unmet-need route for sites outside settlements.

89%

Housing Delivery Test 2025

2,096 homes delivered against 2,351 required, 2022-23 to 2024-25

Under 95%: action plan

Housing Delivery Test 2025

Homes needed and homes built

West Suffolk was formed by reorganisation and is scored as one council across its whole area; gov.uk publishes the three-year totals only.

YearHomes requiredHomes built
Three years2,3512,096

Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.

At planning committee

Committee approval rate

Committee approval rate

83.8%

Of 716 decisions taken at West Suffolk’s planning committee in Searchland’s data, 83.8% were approved.

Source: Searchland, Committee Explorer, authority export, read 27 October 2026.

The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.

From the council’s own documents

Supply, plan and levy

Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.

Five-year housing land supply

6.02 years

At 1 April 2026, five years or more on the council’s own figure. The figure is measured against the adopted plan requirement of 765 homes a year, with a shortfall of 87 homes and a 20 per cent buffer added, over the five years from 1 April 2026 to 31 March 2031.

Source: Assessment of the supply of housing land in West Suffolk, published August 2026.

Local plan

West Suffolk Local Plan 2024-2041

Adopted 15 July 2025. The council says the plan supersedes any previously adopted local plan documents, and made neighbourhood plans also form part of the development plan.

The council has started a new West Suffolk Local Plan 2045 under the new plan-making system. A scoping consultation ran from 16 June to 28 July 2026, and Gateway 1 is set for 29 October 2026. The timetable puts consultation on the proposed plan in June to July 2028, submission in October 2028 and adoption in May 2029.

Sources: the adopted plan; West Suffolk Local Plan 2045 Timetable page (in effect from 16 June 2026, reviewed 14 October 2026). Status checked 25 October 2026.

Community Infrastructure Levy, 2026

No CIL in force

Contributions are sought through section 106 agreements instead; the page lists the council's 2024 to 2025 infrastructure funding statement.

Source: West Suffolk Council, Developer contributions page.

Under the NPPF

What the result means for a site

The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.

The result is below 95%, so from 18 August 2026 the council must prepare an action plan. The published result is not below 75%, so the test does not on its own deem an unmet need for housing to exist.

“Where delivery falls below 95% of the requirement over the previous three years, the authority should prepare an action plan to assess the causes of under-delivery and identify actions to increase delivery in the future;”

NPPF, Annex D, paragraph 12(a), page 119

On the council’s own figure of 6.02 years (below) the council can demonstrate a five-year supply, so the unmet-need route in policy S5(1)(j) is not open on supply either. Supply figures are often contested at appeal, and a later finding can differ.

The West Suffolk Local Plan 2024-2041 was adopted on 15 July 2025. Until 15 July 2030, a local housing need figure above the plan's requirement is not, by itself, evidence of unmet need.

“Where a local planning authority can demonstrate a five year supply of deliverable housing sites (with the appropriate buffer) and where the Housing Delivery Test indicates that the delivery of housing is more than 75% of the housing requirement over the previous three years, for the purposes of policy S5(1)(j), if the most up-to-date local housing need figure (calculated using the standard method set out in Annex D) is greater than the housing requirement set out in adopted development plan policies, this should not be considered as evidence of unmet need, for a period of five years from the date of the plan's adoption.”

NPPF, Annex A, paragraph 3, page 99

In the Green Belt

Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.

“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”

NPPF, Footnote 41, page 63

What it does not do

None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.

“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”

NPPF, Policy S5(2), page 26

Across the boundary

Councils next to West Suffolk

A site near the edge of West Suffolk may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.

CouncilHDT 2025Five-year supplyCommittee approval rate
Babergh147% 95% or more: no consequence4.68 years at 1 April 202581.3% of 288
Braintree150% 95% or more: no consequence5.32 years at 1 April 2024 (out of date)80.1% of 1,474
Breckland144% 95% or more: no consequenceNot yet checked82.7% of 369
East Cambridgeshire116% 95% or more: no consequence6.17 years at 1 April 202565.7% of 207
King's Lynn and West Norfolk100% 95% or more: no consequence6.2 years at 1 April 202673.9% of 884
Mid Suffolk227% 95% or more: no consequence6.73 years at 1 April 202571.7% of 385
South Cambridgeshire148% 95% or more: no consequence7.83 years at 1 April 202670.4% of 825

Councils that share a boundary with West Suffolk on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.

Check a site in West Suffolk

Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.

Check a site in West Suffolk

Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.