If we think you should walk away, we will say so. Free first pass, answered in two working days ·  Send a site
Land PassIndependent land checks

Councils · England

Wyre: housing land supply and delivery

Wyre delivered 237% of the homes it needed in the three years to 31 March 2025. That passes the test and carries no consequence, so whether the unmet-need route opens turns on the five-year supply.

237%

Housing Delivery Test 2025

2,034 homes delivered against 859 required, 2022-23 to 2024-25

95% or more: no consequence

Housing Delivery Test 2025

Homes needed and homes built

YearHomes requiredHomes built
2022-23297721
2023-24282676
2024-25280638
Three years8592,034

Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.

At planning committee

Committee approval rate

Committee approval rate

74%

Of 204 decisions taken at Wyre’s planning committee in Searchland’s data, 74% were approved.

Source: Searchland, Committee Explorer, authority export, read 27 October 2026.

The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.

From the council’s own documents

Supply, plan and levy

Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.

Five-year housing land supply

8.36 years

At 1 April 2026, five years or more on the council’s own figure. The figure is measured against the adopted requirement of 296 homes a year with a 20% buffer, for 2026/27 to 2030/31.

Source: Wyre Council Housing Monitoring Report, August 2026, published August 2026.

Local plan

Wyre Local Plan (2011-2031) (incorporating partial update of 2022)

Adopted 26 January 2023. It replaces the original Wyre Local Plan (2011-2031) but keeps all of its policies except those revised by the partial update.

The council has stopped work on the local plan it had been preparing since 2022, which reached Issues and Options consultation in 2024, and the Preferred Options consultation planned for early 2026 will not go ahead. It will instead prepare a new local plan under the new national system. Before it can start, it must give at least four months' public notice and publish a new local plan timetable.

Sources: the adopted plan; Emerging New Style Local Plan page, Wyre Council (viewed 25 October 2026). Status checked 25 October 2026.

Community Infrastructure Levy

Not yet checked

Whether Wyre charges CIL, and at what rate this year, has not yet been checked for this page.

Under the NPPF

What the result means for a site

The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.

A result of 95% or more carries none of the Framework's consequences. The test on its own does not deem an unmet need for housing to exist.

On the council’s own figure of 8.36 years (below) the council can demonstrate a five-year supply, so the unmet-need route in policy S5(1)(j) is not open on supply either. Supply figures are often contested at appeal, and a later finding can differ.

The Wyre Local Plan (2011-2031) (incorporating partial update of 2022) was adopted on 26 January 2023. Until 26 January 2028, a local housing need figure above the plan's requirement is not, by itself, evidence of unmet need.

“Where a local planning authority can demonstrate a five year supply of deliverable housing sites (with the appropriate buffer) and where the Housing Delivery Test indicates that the delivery of housing is more than 75% of the housing requirement over the previous three years, for the purposes of policy S5(1)(j), if the most up-to-date local housing need figure (calculated using the standard method set out in Annex D) is greater than the housing requirement set out in adopted development plan policies, this should not be considered as evidence of unmet need, for a period of five years from the date of the plan's adoption.”

NPPF, Annex A, paragraph 3, page 99

In the Green Belt

Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.

“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”

NPPF, Footnote 41, page 63

What it does not do

None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.

“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”

NPPF, Policy S5(2), page 26

Across the boundary

Councils next to Wyre

A site near the edge of Wyre may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.

CouncilHDT 2025Five-year supplyCommittee approval rate
Blackpool156% 95% or more: no consequenceNot yet checked77% of 244
Fylde175% 95% or more: no consequence4.35 years at 1 April 202583.3% of 1,099
Lancaster48% Under 75%: unmet need deemed2.4 years at 1 April 2023 (out of date)82.5% of 1,619
Preston460% 95% or more: no consequence5.9 years, agreed or found at appeal85.6% of 758
Ribble Valley425% 95% or more: no consequence2.24 years at 31 March 202678% of 182

Councils that share a boundary with Wyre on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.

Check a site in Wyre

Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.

Check a site in Wyre

Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.