Harborough: housing land supply and delivery

Harborough delivered 139% of the homes it needed in the three years to 31 March 2025. That passes the test and carries no consequence, so whether the unmet-need route opens turns on the five-year supply.

139%

Housing Delivery Test 2025

2,177 homes delivered against 1,569 required, 2022-23 to 2024-25

95% or more: no consequence

Housing Delivery Test 2025

Homes needed and homes built

YearHomes requiredHomes built
2022-23534929
2023-24525757
2024-25510491
Three years1,5692,177

Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.

At planning committee

Committee approval rate

Committee approval rate

83.1%

Of 83 decisions taken at Harborough’s planning committee in Searchland’s data, 83.1% were approved.

Source: Searchland, Committee Explorer, authority export, read 27 October 2026.

The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.

From the council’s own documents

Supply, plan and levy

Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.

Five-year housing land supply

3.1 years

At 1 April 2025, under five years on the council’s own figure. The figure is measured against local housing need of 735 homes a year plus a 5% buffer, and the statement gives it rounded to one decimal place.

Source: Harborough District Council 5 Year Housing Land Supply Statement, 01 April 2025 to 31 March 2030, published 31 October 2025.

Local plan

Harborough Local Plan 2011-2031

Adopted 30 April 2019. The Leicestershire Minerals and Waste Local Plan to 2031 (adopted 25 September 2019) is also part of the development plan.

The new Harborough Local Plan 2020-2041 is at examination. Its Regulation 19 consultation ran from 10 March to 6 May 2025, and the council submitted it to the Secretary of State on 17 April 2026. Stage 2 of the examination hearings starts on 10 November 2026.

Sources: the adopted plan; Examination Latest News page (entry of 24 September 2026), with the Examination Overview and New Local Plan pages for the submission and consultation dates. Status checked 24 October 2026.

Community Infrastructure Levy, 2026

No CIL in force

The council's latest Infrastructure Funding Statement, for 2022/23, says Harborough does not have a CIL charge, so contributions are secured through section 106 agreements.

Source: Infrastructure Funding Statement 2022/23 (the latest listed on the council's Infrastructure Funding Statement page).

Under the NPPF

What the result means for a site

The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.

A result of 95% or more carries none of the Framework's consequences. The test on its own does not deem an unmet need for housing to exist.

The unmet-need route in policy S5(1)(j) is still open in Harborough, because the council’s own figure is under five years of supply (below). Policy S5(1)(j) applies where the council “cannot demonstrate a five year supply of deliverable housing sites or scores below 75% in the most recent Housing Delivery Test”.

In the Green Belt

Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.

“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”

NPPF, Footnote 41, page 63

What it does not do

None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.

“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”

NPPF, Policy S5(2), page 26

Across the boundary

Councils next to Harborough

A site near the edge of Harborough may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.

CouncilHDT 2025Five-year supplyCommittee approval rate
Blaby86% Under 95%: action plan2.78 years at 1 April 202590.9% of 11
Charnwood62% Under 75%: unmet need deemed3.56 years at 1 April 202690.3% of 186
Leicester39% Under 75%: unmet need deemed5.2 years at 1 April 2024 (out of date)89.7% of 757
Melton190% 95% or more: no consequence7.6 years at 1 April 202667.9% of 502
North Northamptonshire108% 95% or more: no consequenceNot yet checked91.3% of 321
Oadby and Wigston152% 95% or more: no consequence6.07 years at 31 March 202585.8% of 106
Rugby187% 95% or more: no consequence3.4 years at 1 April 202581.9% of 287
Rutland89% Under 95%: action plan4.64 years at 31 March 202681.6% of 239
West Northamptonshire104% 95% or more: no consequence4.3 years at 1 April 202681.9% of 568

Councils that share a boundary with Harborough on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.

Check a site in Harborough

Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.

Check a site in Harborough

Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.