Rutland: housing land supply and delivery

Rutland delivered 89% of the homes it needed in the three years to 31 March 2025. That requires the council to prepare an action plan. On its own it does not open the unmet-need route for sites outside settlements.

89%

Housing Delivery Test 2025

346 homes delivered against 388 required, 2022-23 to 2024-25

Under 95%: action plan

Housing Delivery Test 2025

Homes needed and homes built

YearHomes requiredHomes built
2022-2314296
2023-24123110
2024-25123140
Three years388346

Source: Housing Delivery Test: 2025 measurement, Ministry of Housing, Communities and Local Government, results table (ODS), published 17 August 2026. gov.uk rounds each result to the nearest 1%; the figures here are as published.

At planning committee

Committee approval rate

Committee approval rate

81.6%

Of 239 decisions taken at Rutland’s planning committee in Searchland’s data, 81.6% were approved.

Source: Searchland, Committee Explorer, authority export, read 27 October 2026.

The committee approval rate is the share of decisions taken at the council’s planning committee that were approved, in Searchland’s Committee Explorer data. Most applications are decided by officers under delegated powers and never reach the committee, so it is not the council’s overall approval rate, and it is not the chance that a particular site gets permission. The number of decisions behind each rate is given, so that a high rate on a handful of decisions is read for what it is.

From the council’s own documents

Supply, plan and levy

Printed only where Land Pass has read the council’s own document. Each one gives its source and date, and a figure more than a year old says so.

Five-year housing land supply

4.64 years

At 31 March 2026, under five years on the council’s own figure. The figure is measured against local housing need of 269 homes a year plus a 20% buffer, which is 1,614 homes over five years, against a supply of 1,499 homes.

Source: Five-year land supply report 1 April 2026 to 31 March 2031, published July 2026.

Local plan

Rutland Core Strategy Development Plan Document

Adopted 11 July 2011. The Site Allocations and Policies Development Plan Document (October 2014) is also part of the development plan. The council's own planning.data.gov.uk local-plan record for the Core Strategy (entity 4221089) gives the same start date, 11 July 2011.

The Rutland Local Plan 2021-2041 was submitted for examination on 28 February 2025, and consultation on its main modifications ended on 7 September 2026. In the scoping report it put out for consultation in September 2026, the council says it expects to adopt that plan later in 2026. The council has also started a further plan for 2026 to 2046 under the new system: its scoping consultation ran from 10 September to 14 October 2026, and the timetable shows adoption planned for 30 April 2029.

Sources: the adopted plan; Rutland Local Plan 2026-2046 Scoping Report, consulted on from 10 September to 14 October 2026, on the council's consultation portal (main modifications: https://rutland.oc2.uk/document/55; submission date: https://www.planning.data.gov.uk/entity/5101307; planned adoption: https://www.planning.data.gov.uk/entity/5110487). Status checked 25 October 2026.

Community Infrastructure Levy

Not yet checked

Whether Rutland charges CIL, and at what rate this year, has not yet been checked for this page.

Under the NPPF

What the result means for a site

The National Planning Policy Framework in force since 17 August 2026. The policy text is quoted word for word.

The result is below 95%, so from 18 August 2026 the council must prepare an action plan. The published result is not below 75%, so the test does not on its own deem an unmet need for housing to exist.

“Where delivery falls below 95% of the requirement over the previous three years, the authority should prepare an action plan to assess the causes of under-delivery and identify actions to increase delivery in the future;”

NPPF, Annex D, paragraph 12(a), page 119

The unmet-need route in policy S5(1)(j) is still open in Rutland, because the council’s own figure is under five years of supply (below). Policy S5(1)(j) applies where the council “cannot demonstrate a five year supply of deliverable housing sites or scores below 75% in the most recent Housing Delivery Test”.

In the Green Belt

Policy S5 does not apply in the Green Belt. There the grey belt route in policy GB7(1)(g) needs an evidenced unmet need for the type of development, and footnote 41 defines it for housing as no five-year supply, including any buffer, or a Housing Delivery Test result below 75%.

“Which, in the case of applications involving the provision of housing, means the lack of a five year supply of deliverable housing sites, including the relevant buffer where applicable, or where the Housing Delivery Test result was below 75% of the housing requirement over the previous three years;”

NPPF, Footnote 41, page 63

What it does not do

None of this makes a particular site acceptable. Under policy S5(2), a proposal that fails one of the national policies saying development should be refused in specific circumstances is likely to have its benefits substantially outweighed.

“In applying this policy, the circumstances in which the benefits of approving development proposals are likely to be substantially outweighed by adverse effects include, but are not restricted to, situations where the development proposal would fail to comply with one of the national decision-making policies which state that development proposals should be refused in specific circumstances.”

NPPF, Policy S5(2), page 26

Across the boundary

Councils next to Rutland

A site near the edge of Rutland may sit in a neighbouring council, and the figures can differ sharply across the line. Each name opens that council’s page.

CouncilHDT 2025Five-year supplyCommittee approval rate
Harborough139% 95% or more: no consequence3.1 years at 1 April 202583.1% of 83
Melton190% 95% or more: no consequence7.6 years at 1 April 202667.9% of 502
North Northamptonshire108% 95% or more: no consequenceNot yet checked91.3% of 321
Peterborough100% 95% or more: no consequence4.38 years at 31 March 202568.1% of 499
South Kesteven97% 95% or more: no consequence4.07 years at 1 April 2024 (out of date)79.3% of 502

Councils that share a boundary with Rutland on the Office for National Statistics’ December 2024 local authority boundaries. Sources for each figure are on each council’s page.

Check a site in Rutland

Send the site and the first pass reads it against these figures, the settlement boundary, the Green Belt and flood maps, and the decisions on the land around it. Free, within two working days.

Check a site in Rutland

Every figure on this page comes from the source linked beside it, as at the date given. Nothing is rounded up. Page built 30 October 2026 from the Housing Delivery Test 2025 results, Searchland’s Committee Explorer export and Land Pass’s council fact-pack. It is decision support, not planning advice.